Construction work of Sewage Pump Station Project Jeddah Airport, Saudi Arabia
Project Partners:
| Role |
Organization |
| Owner | National Water Company (NWC) |
| Consultant | Bayt Al Khibra for Engineering Consultants |
| Main Contractor | Thrustboring Construction Co. Ltd. / Tamimi Group |
| Subcontractor | EPF General Contracting Co. |
| Project Location | Airport Area, Jeddah City, Kingdom of Saudi Arabia |
Construction of a Sewage Pump Station near the Airport Area in Jeddah under NWC’s infrastructure development program.
The Pump Station project enhances wastewater management for the airport zone.
EPF delivers all work in coordination with TCC, Bayt Al Khibra, and NWC.
Quality & Safety Compliance:
• Workers equipped with PPE.
• Rebar and formwork executed under HSE supervision.
• Materials inspected regularly per consultant specifications.
Current Work Progress:
Foundation-level works successfully initiated by the EPF site team.
Project Update – November 2025
Phase 6
Wall Reinforcement & Formwork
Vertical reinforcement and chamber wall formwork progressing.
Segments aligned and prepared for upcoming concrete activities.
↓
Phase 5
Footing Concrete Works
Footing concrete placed and finished under consultant monitoring.
Curing and QA checks completed.
↓
Phase 4
Reinforcement Installation of Main Shaft Building
Reinforcement cages assembled and tied within foundation areas.
Grid alignment checked before advancement.
↓
Phase 3
Waterproofing
Surface preparation and Waterproofing of collection chamber blinding concrete.
↓
Phase 2
Formwork & Rebar Layout
Timber formwork set for footing zones.
Rebar layout prepared and verified.
↓
Phase 1
Site Preparation
Site clearing, leveling, and excavation completed.
Foundation layout verified by consultant.